Rubb Hall Construction in Skaramagkas Accommodation Facility
Project Description
Construction Works
- Construction of the Rub Hall base from C20/25 concrete, reinforced with T131 structural mesh, dimensions of 10.40mx37.00m & of thickness 0.20m.
- Complete co-assembly of the Rub Hall according to the manufacturer’s instructions.
- Construction of the grid- metal construction of the Rub Hall compartments.
- Creation of internal partitions from plasterboard.
- Installation of a suspended ceiling made of mineral fibres.
- Painting of internal partitions.
- Supply, transport and installation of double doors at the front and rear entrances of Rub Hall.
- Supply and installation of external synthetic frames in the internal corridor with opening panels.
- Construction of fencing around the perimeter of Rub Hall.
Electromechanical Works
- Supply, transport and installation of (1) Rub Hall general distribution electrical switchboard.
- Supply, transport and install (6) electrical switchboards in the accommodation areas.
- Supply, transport and complete installation of all Rub Hall interior & exterior lighting fixtures.
- Electrical works for routing of all required wiring, installation of switches & sockets & connection of electrical appliances.
- Supply transportation & complete installation of equipment for WIFI coverage in Rub Hall & complete & proper operation of the system.
- Electrical certification of the installation & issue of an electrical installer’s declaration of responsibility.
- Supply, transport & installation of (11) split unit heat pumps.
- Supply, transport & installation of (2) solar water heaters
- Supply & installation of (3) septic underground watertight cesspools with a minimum net total capacity of 25m3.
International Organization for Migration, IOM
Accommodation Facility of Skaramagkas, Attica, Greece
May 2020
(40) days